Project: Jask International Crude Oil Export and Import Terminal
Clients: Petroleum Engineering and Development Company (PEDEC), National Iranian Oil Engineering and Construction Company (NIOEC), and Pars Oil and Gas Company (POGC)
Project Start Date: 2018
Project Sector: Offshore Projects
Project Location: Kuh Mobarak, Jask, Hormozgan Province, Iran
Project Description:
The Jask International Crude Oil Export and Import Terminal is located along the coast of the Gulf of Oman, west of Jask city and north of Kuh Mobarak village in Hormozgan Province. The facility was designed to handle the export of one million barrels per day of light, heavy, and extra-heavy crude oil, transported from Goreh to Jask through a 42-inch pipeline and stored in the adjacent 10-million-barrel Jask storage facility. The terminal’s purpose is to export crude oil through subsea pipelines and Single Point Mooring (SPM) buoy systems.
Engineering Services Provided:
- Geological, hydrological, climatological, and geotechnical investigations and studies for both onshore and offshore areas.
- Seismic hazard assessment studies.
- Marine desk studies, including hydrodynamic, sedimentation, and coastal morphology studies.
- Offshore geophysical and geotechnical investigations and studies.
- Environmental studies and preparation of the required reports, including obtaining approvals and permits for facility construction from the Department of Environment.
- Non-structural civil defense studies and design, including obtaining the required permits and approvals from the National Civil Defense Organization.
- HAZOP and HAZID studies conducted by a qualified consultant approved by the client.
- Basic design and plot plan development for the marine terminal, including SPM buoy systems, subsea pipelines, and associated Pipeline End Manifolds (PLEMs).
- Basic design and plot plan development for the support jetty, breakwater, and support site.
- Basic design of the onshore terminal, including flow measurement and metering systems; pig launcher and receiver stations for subsea pipelines; pipelines and interconnecting facilities from the Jask storage tank farm tie-in point; administrative buildings, accommodation facilities, laboratories, maintenance workshops, warehouses, and other civil and structural facilities; electrical substations; and pumps, tanks, and associated equipment for supplying and receiving fuel, water, treated wastewater, and other utilities to and from tugboats and marine vessels.
Project Status: Completed in 2019