30-Inch Gas Pipeline from Salman to Siri Island

Project: Detailed Design of the 30-Inch Subsea Gas Pipeline from Salman Field to Siri IslProject: Detailed Design of the 30-Inch Subsea Gas Pipeline from Salman Field to Siri Island

Client: Iranian Offshore Oil Company (IOOC) and Jahanpars Engineering and Construction Company

Project Start Date: 2023 (1402)

Project Sector: Offshore Projects

Project Location: Persian Gulf, Iran

Services Provided:

Engineering services for the 30-inch subsea gas pipeline connecting Salman Field to Siri Island, with a total length of 150 kilometers. The scope of work included:

  1. Verification and validation of basic engineering
  2. Detailed engineering design
  3. Procurement engineering
  4. Review and alignment of engineering documents with installation requirements
  5. Preparation of EPC tender documents

Status: Not specifiedStatus: Not specified